Data centre cooling and mechanical contractors
Chilled water plant, air handling in the hall, direct-to-chip liquid cooling and heat rejection, filterable by service and country.
North America
View region →ACIS Inc. is a commercial HVAC contractor founded in 2002 with offices listed for Dallas, Fort Worth, Austin, Houston and San Antonio. Its projects page lists data centre HVAC as a capability, specifically CRAC and CRAH replacement, critical cooling and chilled water plant upgrades for high-density environments. The company reports around 350 employees and technicians factory-trained on Carrier, Trane, York, Daikin and Smardt equipment.
Anchor Mechanical is a mechanical contractor whose main operation is in the West Loop in Chicago, with further locations in Scottsdale, Dallas, Washington DC, Florida, San Diego, San Francisco and Dublin. Data centres are the first market it lists, and its stated data centre scope includes chiller system installation, maintenance, retrofits and performance testing alongside process piping and building automation. The evidence is a dedicated data centre services page rather than a named project, so the depth of its data centre cooling portfolio is not verifiable from its own site.
Batchelor and Kimball is a mechanical and plumbing contractor working from an office and 90,000 square foot fabrication facility at 2227 Plunkett Road, Conyers, Georgia, inside the Atlanta metro area, with further offices in Athens, Georgia, North Charleston, South Carolina and Pryor, Oklahoma. Its data centre scope covers central energy plants, CRAC and CRAH units, process chilled water, chillers and cooling towers, and the company states it has installed mechanical systems supporting more than 4.77 gigawatts of data centres since 2006. It trades as an EMCOR company.
Bel-Aire Mechanical is a mechanical and HVAC contractor with its office at 4201 N 47th Avenue, Phoenix. Its own project record for the CyrusOne campus at Chandler in the Phoenix metro sets out a closed loop chilled water cooling design with 200-ton CRAH units and 500-ton air-cooled chillers. The firm also lists Charles Schwab, Digital Realty and NTT data centre projects on the same portfolio.
Bellomy Industries and Mechanical Services, trading as BIMS, is a commercial HVAC and refrigeration contractor at 1201 Minters Chapel Road, Grapevine, in the Dallas-Fort Worth metro. Its service lines include computer room cooling, chillers and cooling towers, and it states that its technicians work on cooling systems for DFW data centres, including upgrades and new installations. Evidence is a stated service capability rather than a named data centre project.
Crawford Mechanical Services is a mechanical and plumbing contractor at 408 South Hamilton Court, Gilbert, in the Phoenix metro. Its project list carries a mission critical data centre heat rejection job in Chandler replacing three 600 ton cooling towers with three 800 ton units, together with the supporting structural steel and custom-fitted pipe. The same portfolio records central plant chiller and cooling tower work elsewhere in the valley.
F.E. Moran is a mechanical piping and HVAC contractor with its head office at 2265 Carlson Drive, Northbrook, Illinois, and it names Chicago as one of its service hubs. Its data centre work covers CRAC and CRAH units, chilled water and direct expansion systems, economisers and free cooling, in row and overhead cooling and liquid cooling, supported by a 75,000 square foot prefabrication facility. Both quotes come from the same page.
Kahn Mechanical Contractors is a commercial mechanical contractor at 2787 Irving Blvd, Dallas, trading since 1974. It states that it services chiller plants in data centres across Dallas, Collin, Denton and Tarrant Counties, covering water-cooled and air-cooled machines from 50 tons to more than 1,000 tons. The work is chilled water plant service and repair rather than new data hall construction.
McKenney's is a mechanical contractor with its head office at 1056 Moreland Industrial Boulevard in Atlanta and a second office in Charlotte, North Carolina. Its mission critical group installs and services cooling plant in live data centres, including twelve CRAC units across data halls at the EdgeConneX ATL02 colocation facility in Atlanta. The same market page records a 900 ton air cooled chilled water plant and distribution system for a 1.5MW data centre in Alpharetta, Georgia.
Midsouth Mechanical Contractors is headquartered at 114 Corporate Park East Drive, LaGrange, Georgia, and lists Atlanta among its own locations, stating it has served the Atlanta area for over 25 years. Its data centre scope covers chilled water plants with chillers, cooling towers and hydronic piping, CRAH and CRAC air handling, and direct to chip, cold plate and immersion liquid cooling, together with heavy rigging and equipment setting. Two quotes are given because no single page carries both the metro presence and the cooling scope.
Professional Piping Systems is a mechanical piping contractor based at 738 South 52nd Street, Tempe, in the Phoenix metro. Its data centre and mission critical page records chilled water piping, chiller and CRAH installation work inside live data halls, including a chiller canopy project at a mission critical facility in Phoenix. Work is carried out with in-house fabrication and hot tapping on occupied sites.
Staxmatic Mechanical Systems is a mechanical piping contractor with its Dallas office at 16051 Addison Rd, Addison, Texas. Its data centre page describes prefabricated chilled-water headers, pump skids and complete mechanical rooms built and tested off site, along with liquid and air cooling layouts for mission critical facilities. Fabrication is ASME certified and includes robotic welding and hydrotesting.
TDIndustries is a mechanical construction and facilities services company headquartered at 13850 Diplomat Drive, Dallas, with a further office in Tempe, Arizona. Its own project record for a 180MW, one million square foot multi-data-hall complex in North Texas covers design-assist mechanical work including a central heating and cooling plant, airside ventilation and evaporative cooling. Caveat for the reviewer: the project page gives the location only as North Texas, not Dallas by name, so the metro tie rests on the Dallas headquarters recorded on the same site.
Willis Mechanical is a family owned mechanical contractor at 1850 Beaver Ridge Circle, Norcross, Georgia, serving metro Atlanta. It works on chiller plants and critical HVAC for data centre facilities, concentrating on plant capacity upgrades, end of life replacements and phased retrofits carried out around change windows in facilities that are already running rather than on new build.
Browse by country
Run a cooling or mechanical contracting firm?
Send us the services you cover, the countries and cities you work in, and your website, and we will add your firm to this listing.
This is an independent listing compiled from public information. Listings are not endorsements, and Fernable has no commercial affiliation with the companies listed.
Common questions
Can direct-to-chip cooling be added to a hall that is already live?
Usually yes, and it is becoming routine, but the cost sits in access rather than equipment. Expect out-of-hours tie-ins, temporary cooling, and racks decanted to make room for coolant distribution units and manifolds. If the original installation left no valved provision on the loop, the tie-in needs pipe freezing or a planned drain-down of a section, which is a different risk conversation entirely.
Do chilled water temperatures have to change for liquid cooling?
Direct-to-chip runs on much warmer facility water than a CRAH coil wants, so a mixed hall usually ends up with two regimes: cold water for the air side, warmer water for the liquid side, either blended or served by separate plant. Raising the whole plant to suit liquid strands the air-cooled load you still have. Decide that split before sizing anything.
Who carries the design liability on a mechanical package?
It depends on the split you tender. A prescriptive design keeps it with the consultant and the contractor prices the drawings. A contractor-designed portion or a full performance specification moves it, and then the professional indemnity cover, its limit, whether it is project-specific, and whether it answers a fitness for purpose clause all matter. Agree that before award, never after.
How long do the long-lead mechanical items take?
Quoted lead times on chillers, coolant distribution units, plate heat exchangers, large valves and drives move with the order book, so any figure you are given is a snapshot at the date of that quote, not a constant. In tight markets chillers have run past a year. Plan to order before the design is frozen, and accept that the design then follows the machine.
What has to be finished before IT load goes on?
Pressure testing, flushing and chemical cleaning with a water sample analysed against the specification, filtration down to the stated cleanliness target, balancing, functional testing of each system, then integrated systems testing on load banks including failure modes and a transfer to standby power. Cleanliness certificates are not paperwork for its own sake: a dirty loop blocks cold plates.
Open cooling towers or air-cooled plant?
That is a site trade, not a preference. Towers use less power and more water, need a legionella regime and a discharge route, and depend on design wet bulb. Air-cooled plant uses no water, wants more area and more power, and derates on the hottest days. Water permits, boundary noise limits, land and your own reporting commitments usually decide it.
What the mechanical package actually covers
The package runs from the heat rejection plant in the yard or on the roof to the terminal equipment in the hall: chillers, pumps, buffer vessels and thermal store, headers, valves, pipework and insulation, then CRAH or CRAC units, fan walls, in-row units, rear-door heat exchangers and coolant distribution units. On a liquid job the contractor usually takes the secondary loop up to the rack manifold and stops there, because cold plates, hoses and quick disconnects arrive with the servers. That interface line is where the first argument on any liquid retrofit happens.
What sits outside the package matters as much. Power to the mechanical plant, the motor control centre and the field wiring are usually electrical scope. Structural steel, plinths, roof penetrations and builder's work usually belong to someone else. Acoustic screening is sometimes nobody's until the planning condition is read properly. And a firm that builds new plantrooms is not automatically the firm you want cutting into a loop above live racks, or holding the maintenance contract afterwards. Most contractors offer all three, new build, retrofit and service, and are genuinely good at one or two.
The two jobs, and why they price differently
On a new build you are buying a plantroom, an external plant yard, riser pipework and a hall fit-out delivered in tranches as capacity is sold. Phasing is the part that catches people out. Plant is sized for the finished building but installed in stages, so the first hall runs the system at a fraction of design load, and pump control, chiller staging, minimum flow and coil selection all have to work down there as well as at the top. A scheme that only behaves at full load is a scheme that will be run manually.
The other job, now at least as common, is intervening in a building that already carries IT load. Adding direct-to-chip capacity, replacing end-of-life chillers, changing refrigerant, recoiling air handling units, cleaning and treating a loop that has been neglected for a decade. There is no hot work over live equipment, tie-ins need either valved provision left by the original installer or pipe freezing, work happens out of hours, temporary chillers arrive on hire, and racks get decanted to find floor space for coolant distribution units. Cost and programme there behave nothing like new build.
Chilled water, air, liquid and heat rejection
Chilled water is still the backbone at scale: chillers, primary and secondary pumping, a thermal store sized to hold the hall through a chiller restart after a transfer, and headers valved so any machine or pump can be isolated without dropping a path. Air terminals split between CRAH units fed from that loop and CRAC units carrying their own refrigerant circuit and external condensers, with fan walls and in-row units now normal in large halls. Heat rejection is a site-specific trade: open towers, air-cooled chillers, dry coolers, adiabatic assist, each swapping water against power, area and noise.
Liquid is the live argument. Direct-to-chip arrives as a retrofit problem as often as a new build one, and a coolant distribution unit brings a secondary loop with water quality, filtration, material compatibility and leak containment requirements that ordinary building services pipework has never had to satisfy. Rear-door heat exchangers are a lighter intermediate step. Immersion is a different discipline again, with fluid handling, floor loading and, for some fluorinated fluids, an unresolved regulatory question. Nobody should tell you the industry has converged. Air, rear-door, single-phase direct-to-chip and immersion are all being built, sometimes inside one estate.
How this work is quoted, and what moves the number
This work is tendered against a drawing set, a specification, a plant schedule and a programme. You get a lump sum, usually with a schedule of rates for variations and provisional sums for what is not yet drawn. What that sum actually covers depends on the design responsibility split. A prescriptive specification keeps the design with the consultant and the contractor prices what is drawn. A performance specification, or a contractor-designed portion, moves capacity and efficiency warranties onto the bidder. Those two routes produce different numbers and very different risk, so settle which you are tendering before you compare bids.
What moves the number: long-lead plant, and the awkward fact that chillers, coolant distribution units, plate heat exchangers, large valves and drives are often ordered before the design is frozen, so the order fixes cost and the design then bends around the machine. After that, working over live load, pipework material and jointing method, prefabrication extent, insulation and vapour sealing, commissioning scope, spares and attendance, and who carries flushing and water treatment. Freight and currency on imported plant. Read the exclusions first: builder's work, power to the plant, acoustic treatment and integrated systems testing are the usual gaps.
Records, certificates and the regimes that outlive the project
Expect pressure test certificates, flushing and chemical cleaning records with a laboratory water analysis, filtration results measured against a stated cleanliness target rather than a tick, welding procedure specifications with current welder qualifications and non-destructive testing reports on the proportion of joints specified, valve and plant certification, refrigerant charge and leak records, lifting plans, then as-built drawings and an operation and maintenance manual somebody can still use in five years. Pre-commission cleaning of pipework has its own published guidance and its own sign-off, and it belongs before IT load, not alongside it.
Then the statutory layer. Open towers and evaporative equipment bring a legionella risk assessment, a written water safety plan, registration with the local authority in many jurisdictions, and a logged monitoring routine with named responsibility attached. Refrigerant work needs certified operatives and a charge log, and the move to lower global warming potential fluids, some of them flammable, brings plantroom ventilation, gas detection and a different design case. Pressure equipment rules can apply depending on fluid and pressure. Commissioning records are where a client witnessing regime and any certification scheme meet, and where programmes quietly lose weeks.
Where these projects actually go wrong
The electrical interface is the classic scope gap. Who supplies the variable speed drives, who wires actuators and sensors, who terminates in the mechanical switchboard, whose scope is chiller control power, and which pumps sit on uninterruptible supply so water keeps moving through a transfer to standby generation. Thermal ride-through depends on that last answer and on the thermal store, not on goodwill. When the split is left to two contractors to sort out on site, you find the truth during the black building test, at the point in the programme where there is no time left.
Controls are the second. The sequence of operations is the most consequential document in a mechanical package and the one most often unfinished at installation. The contractor's controls subcontractor and the separate building management integrator each assume the other owns chiller sequencing, pump staging, valve strategy, setpoint reset and alarm handling. Points lists arrive incomplete, graphics arrive late, and the plant runs in hand because nobody has signed the sequences off. Part-load behaviour in a half-occupied building is where that hurts most, and it is exactly the condition nobody tests properly.
The third is water. A loop flushed to a certificate but never to a particle count. Oxygen ingress into a system everyone calls closed but which is topped up weekly. Mixed metals, depleted inhibitor, microbiological growth, corrosion under insulation whose vapour seal failed on a chilled line years ago. On a secondary liquid loop the same neglect blocks cold plates, and the consequence lands on IT rather than on a coil. Add the retrofit special: a tie-in with no isolation provision, a leak over live racks, and a crane window that closed while the plant sat in a yard.
How to build a shortlist
Ask for projects of the same shape rather than the same value. A live retrofit under a containment system is different work from a greenfield plantroom, and the reference list should show which one you are buying. Ask who held the design on those jobs and who carried the liability, then get the professional indemnity position in writing: the limit, whether it is project-specific, and whether it responds to any fitness for purpose wording your contract imposes, because most policies do not. Ask about welding capability, prefabrication, and whether spools are built off site.
Then test capacity and continuity. Who would actually be on site, what else that team is committed to in your window, whether commissioning engineers are employed or hired in, and which firm does their controls. On liquid, ask what they have commissioned and handed over rather than what they can quote, because the installed base is young and every reference list is short. The listings here are factual and drawn from public information. They are not a ranking and not an endorsement: use them to assemble a tender list, then run your own diligence on what is on it.
Why location changes the mechanical answer
Climate and water set the answer before anyone opens a drawing. Design wet bulb decides what evaporative heat rejection can achieve and therefore what chilled water temperatures are realistic. A hot, dry site pushes towards air-cooled plant with adiabatic assist, which trades the water argument for more yard, more electrical load and a harder design day. Water is now a permitting question as much as an engineering one, and the discharge consent for tower blowdown, with its dissolved solids and biocide residual, constrains schemes as often as the supply side does.
Rules and people vary just as much. Energy codes, efficiency reporting, heat reuse obligations, refrigerant restrictions, seismic restraint and boundary noise limits differ by jurisdiction and change plant selection, not only paperwork. So does the labour market: whether pipefitters and commissioning engineers are available when your programme needs them, how site agreements work, and what out-of-hours retrofit labour costs. And the plant has to physically arrive. Port capacity, road route, bridge and gradient limits, a crane position and a lift path for a chiller are geography problems that land on the critical path.