Skip to main content
HV and substation

High-voltage and substation services

Grid connection, substation design and build, high and medium voltage testing, protection relay setting and transformer service, listed by country and city.

15 providers

North America

View region
A

Aldridge Electric is an electrical and civil infrastructure contractor headquartered at 844 E Rockland Rd in Libertyville, Illinois, within the Chicago metro. On hyperscale data centre and other mission critical sites it self-performs medium voltage, substation and temporary power scopes and provides commissioning support services. Its substations practice covers turn-key construction from 12 kV to 765 kV with air insulated and gas insulated switchgear, including testing and commissioning.

Substation buildHV testing
A

Allison-Smith Company is an Atlanta electrical contracting and engineering firm based at 1869 South Cobb Industrial Blvd SE in Smyrna. Its ASTesting group is certified to National Electrical Testing Association standards and carries out medium voltage terminations, testing and installation, relay testing and calibration, transformer testing and breaker testing. It also runs short circuit, coordination and arc flash studies.

HV testingProtection and relays+1
B

Burns and McDonnell is an engineering and construction firm with an Atlanta office at 4004 Summit Blvd NE that serves the south-east. Its Atlanta team provides programme and construction management for the Georgia Power Grid Investment Plan, under which around 200 miles of transmission line are being rebuilt and 36 transmission and distribution substations enhanced. Electrical transmission and distribution is one of the Atlanta office's stated growth areas.

Substation buildGrid connection
C

CBS Field Services is a NETA accredited testing company with its head office in Phoenix. It tests, maintains and repairs low, medium and high-voltage apparatus on equipment rated from 480 V to 345 kV, including utility substations and data centres. Listed work covers substation maintenance and testing, protective relay testing, transformer testing and switchgear testing.

HV testingProtection and relays+1
C

Cleveland Electric is a specialty electrical contractor at 3715 Northside Parkway NW in Atlanta, with a field service group covering north and central Georgia. Its field services include complete substation maintenance, relay and meter calibration, relay repair, cable high pot testing, transformer repair and low and medium voltage switchgear testing. The company lists an Equinix data centre in Atlanta among its field service and testing projects.

HV testingProtection and relays+1
E

Emerald Transformer repairs, remanufactures and services power transformers and associated substation equipment, and runs a facility at 2132 South 5th Avenue in Phoenix alongside its head office in McKinney, Texas. Field crews handle on-site repair, oil processing and retrofilling, electrical testing and the commissioning of new substations. The company also carries out substation field decommissioning and laboratory oil analysis.

Transformer serviceHV testing
G

Great Southwestern Construction is an MYR Group subsidiary that works from offices in Mansfield and Alvarado in the Dallas-Fort Worth area. It has built and maintained substation, distribution and transmission assets for Oncor, the North Texas utility, under a master services agreement since 2014. Its wider capabilities include substation construction and energised transmission work.

Substation buildGrid connection
L

Linxon delivers turnkey alternating current substations and holds the engineering, procurement and construction contract for the Arizona Public Service 230 kV Goodyear substation, which supports a data-centre expansion in the Phoenix area. Its scope on that project runs from design and engineering through construction, testing and commissioning. Its contact page lists a Phoenix office at 2398 E Camelback Rd.

Substation buildHV testing
P

Priority Power develops, builds and operates electrical infrastructure, covering grid interconnection and utility approvals, substation design and construction, and privately owned transmission and distribution from 12.5 kV to 345 kV. It lists offices at 12700 Park Central Drive in Dallas and on East Lamar Boulevard in Arlington. Data centres and high performance computing are among the sectors it names.

Grid connectionSubstation build
Q

Quad Plus is an electrical engineering and field service company headquartered in New Lenox, Illinois, with a second Illinois office in Joliet, both inside the Chicago metro. Its field team works to National Electrical Testing Association standards on medium voltage cables and transformers, switchgear and protective relays in data centres. Services include acceptance testing, commissioning, full-system startup support and relay settings and drawing verification.

HV testingProtection and relays+1
S

Sargent and Lundy is an engineering firm headquartered at 77 W Wacker Drive in Chicago, with a separate Atlanta-area office in Norcross, Georgia. Its grid team works on distribution substations, transmission switchyards, overhead and underground transmission and interconnection planning, including large-load interconnection support for data centres. Its data centre practice covers high and medium voltage substation design and campus layouts that size interconnection load applications.

Grid connectionSubstation build
S

Shermco Industries is a NETA accredited electrical testing organisation with its head office in Irving, Texas. Field services cover protection and control work from relay settings and relay testing through acceptance testing, commissioning and startup, plus transformer repair and testing, oil processing and low, medium and high-voltage breaker and switch testing. Data centres are one of the industries it lists.

HV testingProtection and relays+1
S

Spark Testing is an electrical testing and maintenance company with a Dallas-Fort Worth office at 4900 Diplomacy Road in Fort Worth, alongside Canadian offices in Edmonton and Hamilton. It performs substation testing, commissioning and startup, protective relay testing across transmission, bus differential and transformer differential schemes, and transformer testing to NETA and IEEE methods. Other work covers medium and high-voltage breaker testing, ground grid testing and cable diagnostics.

HV testingProtection and relays+1
S

Station Power Construction is a Phoenix contractor working on substations and on overhead and underground distribution. Its substation scope covers main switchyard installation, foundations, structural steel erection, bus work, control cable and the setting of circuit breakers, circuit switches, transformers, capacitor banks and reactors. The company works with union craftsmen and is registered with the Arizona Registrar of Contractors.

Substation build
S

Sturgeon Electric is an MYR Group subsidiary that builds high-voltage substations, switching stations, gas-insulated switchgear and interconnect stations from 34.5kV to 765kV. Its Phoenix office on East Watkins Street runs the transmission and distribution side of the business for Arizona. Turnkey scope covers procurement, quality assurance and control, and testing and commissioning.

Substation buildGrid connection

Browse by country

Add a provider to this category

If you know a contractor doing grid connection, substation build, high-voltage testing, protection relay work or transformer service, tell us about them. Listings here are factual and sourced.

This is an independent listing compiled from public information. Listings are not endorsements, and Fernable has no commercial affiliation with the companies listed.

Common questions

Who is my counterparty for a grid connection?

The operator that holds the licence for the network at your site: a distribution operator for most industrial and commercial loads, the transmission operator once the capacity is large enough or the voltage high enough. That is a different organisation from your energy supplier, and in some countries different again from the body that runs the study queue. Establish which licence holder and which application route applies before you brief a designer, because the point of connection they offer sets the substation location, the cable route and often the voltage you build at.

Why does the connection date keep moving, and what can I do about it?

Because it usually depends on reinforcement the operator has to build, sequenced against every other project in the queue and against its own plant deliveries. You cannot compress that by pushing your contractor harder. What does help is applying earlier, asking specifically which upstream works your date is waiting on, pricing a lower first-stage capacity or a flexible connection that can be energised sooner, and taking on the contestable portion of the works where the market you are in allows it.

Can the contractor that builds the substation also commission and test it?

Usually yes, and on smaller schemes that is normal practice. Be clear about what you give up. Independent testing exists because the party that installed the plant is the least likely to find its own wiring error, and on a protection scheme that error has safety consequences. On high-consequence plant, keep primary injection, protection proving and the witness role with someone who did not do the installation, or at least witness the critical tests yourself or through your owner's engineer.

What does NETA accreditation mean, and what is the equivalent in other markets?

In North America it identifies a test agency working to the ANSI and NETA acceptance and maintenance testing specifications, with certified technicians and independence from the installer. Elsewhere the equivalents differ in kind rather than translating directly: in Great Britain, registration under the national electricity registration scheme for contestable connection works plus the operator's own acceptance, and in much of Europe and Asia an accredited certificate for the connection together with authorisation under the site or utility safety rules. Ask which scheme, for which activity, at which voltage.

If a protection setting is wrong, who is responsible?

Whoever the contract says authored and verified that setting, which is why the setting file needs a named author, a named checker and version control from the first issue. Approval by the network operator does not transfer liability to the operator, and a relay left in a test or maintenance configuration is the responsibility of the party that put it there. Treat a setting error as a safety event and investigate it that way rather than adding it to a snag list.

When should I order the transformer and the switchgear?

Earlier than the design feels ready for, and with your eyes open. Order to delivery on power transformers and high-voltage switchgear now runs to many months and on larger units into years, long enough that plant procurement rather than construction sets the programme on a great many schemes. The risk of ordering early is a change that makes the plant wrong, so fix the ratings, the impedance, the fault level assumption and the interfaces first, then release. The risk of waiting is a confirmed connection date that arrives before the plant does.

Where this category starts and stops

This category covers the electrical works between the utility network and your own distribution: the connection itself, the substation that terminates it, and the plant and protection inside it. The boundary runs from the point of connection agreed with the network operator to the incoming terminals of your own switchboard. That takes in the application and the offer, any part of the works you are allowed to build yourself, the civils and cable route, the switchgear, the transformer, the earthing system, the protection and control panels, commissioning and energisation. Downstream distribution, generation plant, standby sets and uninterruptible supplies sit in other categories, even when the same firm will happily quote for them.

These five service lines are grouped together because one drawing set, one operator relationship and one energisation date tie them to each other. A transformer cannot be filled and tested until the civils and the oil containment are finished. Protection cannot be proved until the current transformers are installed and the setting file has been approved. The number of parties is small, but the interfaces between them are sharp and the sequence is close to fixed. That is also why the critical path on this work usually sits with somebody other than your contractor.

What you are usually trying to get done

Most enquiries here come out of one of three situations. You need a new connection, or more capacity than the existing one carries, which starts with an application and a study rather than with a builder. You are replacing or extending plant on a site that already runs, so the job is a tie-in under outage conditions with all the risk that brings. Or you already own high-voltage assets and need them tested, serviced and documented on the cycle your insurer and your own safety rules require. The counterparty, the constraint and the paperwork differ in all three, so a provider strong in one is not automatically right for another.

There is a second set of jobs that get bought late and should be bought early. Reviewing a connection offer before you accept it and pay the security. Commissioning a protection coordination study so the setting file can be written and approved while plant is still in manufacture. An earthing study with step and touch potential calculations before the civils are poured. An arc-flash study before labels and working practices are set. Independent witnessing of another party's factory acceptance tests. Fault investigation after a trip nobody can explain. A spares position for the transformer, decided before you need one rather than after.

The five service lines and what each one involves

Grid connection is a regulatory and commercial process before it is a construction one. You apply to the transmission or distribution operator that holds the licence for your site, receive a budget estimate and then a formal offer with a point of connection, a capacity, a charge and an acceptance window. In several markets part of that work is contestable, meaning an accredited provider can build it to the operator's specification and hand it over for adoption, while the rest stays with the operator whatever you do. Substation build then delivers the asset: foundations, oil containment and fire separation, a building or an outdoor compound, switchgear whether air or gas insulated, cable and terminations, the earthing grid, auxiliary supplies, protection and control panels, and the telemetry interface the operator wants visibility through.

Testing and commissioning proves that what was installed matches what was designed. That means insulation and pressure testing on cable and plant, very low frequency or partial discharge testing where the cable warrants it, contact resistance, breaker timing, gas quality on gas insulated equipment, instrument transformer ratio and polarity checks, earthing measurements, and functional proving of interlocks and trip circuits. Protection relay work is the setting, grading and testing of the scheme that clears a fault: the coordination study, the setting file, secondary injection to prove the relay, and primary injection to prove the whole chain including the instrument transformers and the trip path. Transformer service spans route survey, offloading, oil processing and filling under vacuum, dry out, dielectric checks and tap changer commissioning, then the ongoing work: oil and dissolved gas sampling, bushing tests, cooler and gas relay checks, and the call between site repair and a return to works.

How the work is quoted, and what a lump sum leaves out

There is no rate card for this category and you should be wary of anything presented as one. The work is tendered against a drawing set, a specification and a programme, because the labour content is driven by things specific to the site: the fault level you design for, whether the tie-in is live or dead, how many hours of outage you can get and when, the condition of plant nobody has opened in twenty years, and how much of the existing installation has drawings you can rely on. What you see in practice is a lump sum against employer requirements for design and build, a target cost where the scope is genuinely uncertain, a schedule of rates for recurring test visits, and a call-off day rate for reactive attendance. Keep the operator's charge out of the contractor comparison, or you will be comparing two different things.

A lump sum normally excludes the items most likely to move the outturn. The operator's charges and its own reinforcement works are yours, not the contractor's. So are ground conditions, obstructions, contamination and service diversions, unless a survey was done and priced. Delay caused by the operator, a missed energisation window or an outage that gets moved is almost never at the contractor's risk, and neither is escalation on long-lead plant, where quotations often carry a short validity and an adjustment clause. Costs rise with outage-only and night working, with live-side working under a safety document regime, with restricted access and lifting constraints, with standby time waiting on witnesses, and with every unknown you hand over instead of surveying. If liquidated damages are tied to an energisation date, settle who actually controls that date before you sign.

Approvals, records and the handover pack

The front end is mostly regulatory. An adoption or ownership agreement if somebody else will own the asset. Land rights, wayleaves and easements for the cable route, which are slower than people expect. Planning consent for anything visible. Design approval by the operator, which is a review loop and not a stamp.

The back end is the pack that decides whether anyone is willing to energise and whether you can take custody of the asset. An inspection and test plan with named witness points, agreed before work starts rather than argued over afterwards. Signed test records that match that plan. The protection setting record as commissioned, not as designed, under version control. Switching schedules and the safety documents used. As-built drawings, and asset data in the format the operator's records demand. A gas register for sulphur hexafluoride equipment, environmental and oil containment records, an operating and maintenance manual, a spares list and the warranty terms. An incomplete pack on the day is one of the more common reasons an energisation slips by a month.

Where these projects actually slip

The first and largest cause is not on your site. Connection queues in most mature markets are longer than the build, and the date you are given depends on reinforcement works the operator schedules against its own priorities and its own supply chain. Projects get financed and designed to a connection date the developer cannot influence, then replanned when it moves.

The second is the gap between trades, and it shows up at the terminals. Who supplies and fits the cable terminations and glands. Who bonds the transformer to the earthing grid. Who produces the instrument transformer wiring schedule. Who owns the telemetry points list and its mapping into the operator's system. Who writes the protection settings, and who is entitled to approve them. Who provides the test equipment, and who holds the safety document on the day. The classic version is a design that stops at the cubicle, an installer who assumed the settings came with the relays, and a commissioning engineer on site with no approved setting file and no switching schedule. A scope matrix agreed at tender stage costs an afternoon and saves a week of outage.

The third is commissioning error found late, and this one has safety consequences rather than programme consequences. A current transformer ratio typed into a setting file wrongly. A differential scheme with one polarity reversed, which behaves perfectly until it sees a real fault. An element disabled during proving and never restored. Cable tested after backfill, when nothing can be corrected cheaply. A protection setting error is not a defect for a snag list: it is the difference between a fault that clears in tens of milliseconds and one that does not clear at all. That is what primary injection, independent witnessing and a signed as-commissioned record are buying you.

What to ask before you appoint

Ask for accreditation that matches the actual work rather than a general certificate. Everywhere it means named engineers holding the switching and safety authorisation your site or your operator requires, current calibration certificates for the test sets actually being brought, and sample records from a scheme at your voltage rather than a brochure. Ask who will attend, because the named engineer is scarcer than the firm.

Then settle liability and independence in writing. Who carries design responsibility for the earthing study, the protection coordination and the insulation coordination, and does their professional indemnity cover it. Whether protection and test work is self-delivered or subcontracted, and to whom. Last, availability against your outage window, because a provider who can only come in six weeks is not a cheaper provider.

Why the same scope is a different job elsewhere

The same words in a scope can describe two different projects in two countries, because the counterparty structure differs. In some markets the network is unbundled and a licensed independent operator can own and adopt your substation, which gives you a choice of who builds the connection and who owns it afterwards. In others a vertically integrated utility does all of it, holds an approved vendor list that effectively selects your switchgear and transformer manufacturer, and the contestable idea does not exist at all.

Hardware and competence are local too. The standards family, IEC or ANSI, the frequency, and the voltage classes in use decide whether a relay, a breaker or a transformer is usable at all, and whether a spare can be sourced without a new design. Testing is a travelling trade and specialists do fly, but switching authorisation is specific to a site and often to a country, so an imported engineer may still need local authorisation, an escort, or a locally licensed contractor of record to sign the work off. And the heaviest item on site, usually the transformer, arrives under an abnormal load permit along a route somebody has to survey, which is why delivery occasionally decides the design.